Ridge View Supportive Residential Community Project: June 2024 Update
Ridge View Transitional Housing Operator Request for Proposals - MODIFICATIONS
DOH has modified the Request for Proposals (RFP) for Transitional Housing Operator(s) at Ridge View. The revised RFP has been posted on Rocky Mountain Bidnet and Colorado VSS with the following changes:
- Proposers may choose to apply for either transitional housing service provider, or campus property manager or both components.
- Contractor Selection Schedule - Revised Key Dates:
- June 21, 2024 9:30AM-10:30AM MDT: Optional Site Tour at 28101 E Quincy Ave, Watkins, CO - RSVP to Kelli Barker kbarker@state.co.us by 2:00PM on 6/2/24
- June 24, 2024 2:00PM MDT: Questions Submittal Due
- June 26, 2024 2:00PM MDT: Answers Posted onto VSS/BidNet (Estimated)
- June 28, 2024 2:00PM MDT: Letter of Intent due (non-binding)
- July 31, 2024 2:00PM MDT: Response Submission due
- August 12, 2024: Interviews (Optional & Estimated)
- November 15, 2024: Contract Fully Executed (Estimated)
- January 1, 2025: Project Start Date (Estimated)
Engage With Us
Visit the DOLA Ridge View Supportive Residential Community Webpage to engage on the project.
- View past updates
- Ask a question on the project
- Learn who Ridge View will serve
- Learn about the funding behind the Ridge View project
- See how implementing the Ridge View campus will impact local traffic
Share Ridge View Supportive Residential Community Project: June 2024 Update on Facebook
Share Ridge View Supportive Residential Community Project: June 2024 Update on Twitter
Share Ridge View Supportive Residential Community Project: June 2024 Update on Linkedin
Email Ridge View Supportive Residential Community Project: June 2024 Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends